Fleetwood Dikes and Surrey Lake

Partners: City of Surrey

Contract Value: $2,400,000

This challenging project required a large, complex scope of work to be carried out in a short period of time, including the construction of a parking lot, pedestrian walkway, landscaping and the bulk excavation of 126,000 m3 of topsoil, clay, and peat to create a 5.0 hectare lake and wetland. The excavated materials from this project were utilized to create raised areas for wildlife, and to increase the height of the existing Fleetwood and Serpentine River dykes. A bridge was built over  Bear Creek initially for construction purposes, but was thereafter incorporated into the project’s permanent features as a pedestrian bridge.